Commercial Fitout Timeline NSW: The Typical 12-Week Programme
The 12-Week Median
A typical small to medium commercial fitout in NSW takes 10 to 14 weeks from HoA signing to opening day. The 12-week median is a good planning anchor for cafes, retail, professional services, small medical practices, and small office fitouts under 250m². Larger or more specialised projects (food production, surgical clinics, gyms with custom plant rooms) run longer.
The programme has four phases: HoA to lease (~2 weeks), design (~4 weeks), approval (~2-4 weeks depending on CDC vs CC), and construction (~4-6 weeks). Phases overlap. The programme can compress to 8-9 weeks with experienced consultants and a CDC pathway. It can stretch to 16+ weeks with a council DA, custom long-lead equipment, or services capacity surprises.
The Timeline at a Glance
Week-by-Week
The Three Things That Blow Up the Timeline
A council DA can take 6 to 16 weeks instead of CDC's 2-3 weeks. A Sydney Water trade waste application for food premises can add 4 to 12 weeks if not lodged early. NSW Health approvals for medical and pharmacy premises add similar time.
Mitigation: Confirm at HoA stage which approvals apply. Lodge trade waste applications in week 3-4 in parallel with design, not after CDC.
Custom switchboards: 8-16 weeks. Custom kitchen exhaust hoods: 6-10 weeks. BMS controllers: 6-10 weeks. Specialty equipment (medical autoclaves, walk-in cool rooms, large UPS): 10-20 weeks.
Mitigation: Identify long-lead items in week 2 design brief. Order in week 4 once specification is firm. Do not wait for CDC issue to order.
Discovering mid-build that the existing electrical supply is insufficient adds 4-12 weeks for an authority upgrade. Discovering insufficient water pressure adds 8-16 weeks through Sydney Water. These are dealbreakers for the programme.
Mitigation: Pre-lease services capacity check (week 1, $500-$1,500). Negotiate landlord remediation at HoA stage if existing capacity is insufficient.
Who Needs to Know What
Need engineering for your fitout?
Mechanical, electrical, hydraulic, and fire protection design for Sydney commercial fitouts. Plans approved first time. CPEng qualified.
References
- Environmental Planning and Assessment Act 1979 (NSW), CDC and CC processes
- Sydney Water, Trade Waste application timelines 2026
- NSW Health, Premises approval requirements for medical and pharmacy
- National Construction Code 2025, Section J energy efficiency