Design Memo
CCC-DM-2026-199

Commercial Fitout Timeline NSW: The Typical 12-Week Programme

The 12-Week Median

A typical small to medium commercial fitout in NSW takes 10 to 14 weeks from HoA signing to opening day. The 12-week median is a good planning anchor for cafes, retail, professional services, small medical practices, and small office fitouts under 250m². Larger or more specialised projects (food production, surgical clinics, gyms with custom plant rooms) run longer.

The programme has four phases: HoA to lease (~2 weeks), design (~4 weeks), approval (~2-4 weeks depending on CDC vs CC), and construction (~4-6 weeks). Phases overlap. The programme can compress to 8-9 weeks with experienced consultants and a CDC pathway. It can stretch to 16+ weeks with a council DA, custom long-lead equipment, or services capacity surprises.

The Timeline at a Glance

HoA to Lease Weeks 1-2 Design Weeks 3-6 Approval Weeks 5-7 Construction + Commissioning Weeks 7-12 12-Week Programme CDC pathway. Add 2-4 weeks for council DA. Add 4-12 weeks for trade waste applications.

Week-by-Week

Week 1
HoA
Heads of Agreement signed. Brief architect, building services engineer, and BCA consultant. Order pre-lease services capacity check (electrical, water, gas).
Week 2
Lease & brief
Formal lease drafted by lawyers. Architect produces concept layout. Services capacity check completed. Confirm fitout scope is feasible within existing services.
Week 3
Design
Architect develops detailed layout. Mechanical, electrical, hydraulic, fire engineers begin design in parallel. Long-lead equipment specified (switchboard, exhaust hood, BMS).
Week 4
Design
Engineering disciplines coordinate via clash detection. Section J energy compliance prepared. Order long-lead items (typically 8-12 week delivery, hence ordering now).
Week 5
Approval lodged
Full design package lodged for CDC (if eligible) or CC (after DA). Builder tendered or D&C contract signed. Trade waste application lodged with Sydney Water if applicable.
Week 6
Approval / mobilise
Certifier reviews, raises requests for information. Builder mobilises, orders consumables, books loading dock. Long-lead items confirmed in production.
Week 7
CDC issued / strip out
CDC issued (typically 10-15 business days). Construction starts: strip out, demolition, services disconnections. Site induction with building manager.
Week 8
Rough-in
Mechanical, electrical, hydraulic, fire rough-in. Ducts, conduits, pipework installed in ceiling and walls before linings.
Week 9
Lining & fitout
Plasterboard, painting, joinery, flooring. Long-lead equipment delivered (switchboard, kitchen exhaust hood). Air conditioning units installed.
Week 10
Trades complete
Final fix electrical (light fittings, GPOs, switchboard energised), plumbing fixtures, mechanical commissioning starts. Sign-off begins on AFSS-affected items.
Week 11
Commissioning
Mechanical balancing, BMS commissioning, fire system testing, AFSS re-certification. Defects list compiled.
Week 12
OC & opening
Occupation Certificate issued. Defects rectified. Soft launch / training. Doors open.

The Three Things That Blow Up the Timeline

Risk 1: Approval Delay

A council DA can take 6 to 16 weeks instead of CDC's 2-3 weeks. A Sydney Water trade waste application for food premises can add 4 to 12 weeks if not lodged early. NSW Health approvals for medical and pharmacy premises add similar time.

Mitigation: Confirm at HoA stage which approvals apply. Lodge trade waste applications in week 3-4 in parallel with design, not after CDC.

Risk 2: Long-Lead Equipment

Custom switchboards: 8-16 weeks. Custom kitchen exhaust hoods: 6-10 weeks. BMS controllers: 6-10 weeks. Specialty equipment (medical autoclaves, walk-in cool rooms, large UPS): 10-20 weeks.

Mitigation: Identify long-lead items in week 2 design brief. Order in week 4 once specification is firm. Do not wait for CDC issue to order.

Risk 3: Services Capacity Surprise

Discovering mid-build that the existing electrical supply is insufficient adds 4-12 weeks for an authority upgrade. Discovering insufficient water pressure adds 8-16 weeks through Sydney Water. These are dealbreakers for the programme.

Mitigation: Pre-lease services capacity check (week 1, $500-$1,500). Negotiate landlord remediation at HoA stage if existing capacity is insufficient.

Who Needs to Know What

Need engineering for your fitout?

Mechanical, electrical, hydraulic, and fire protection design for Sydney commercial fitouts. Plans approved first time. CPEng qualified.

Get a Quote → 📞 0468 033 206

References

  1. Environmental Planning and Assessment Act 1979 (NSW), CDC and CC processes
  2. Sydney Water, Trade Waste application timelines 2026
  3. NSW Health, Premises approval requirements for medical and pharmacy
  4. National Construction Code 2025, Section J energy efficiency

Related design memos