Electrical

Maximum Demand Calculations for Commercial Buildings

Date: 30 June 2025 Ref: CCC-DM-2025-056 Standard: AS/NZS 3000:2018 Section 2

1. Purpose

This memo explains how to calculate maximum demand for commercial buildings under AS/NZS 3000:2018. You need accurate maximum demand figures to size consumer mains, submains, distribution boards, and protective devices.

Get the numbers wrong and you end up with undersized cables, nuisance tripping, or overloaded switchboards. Get them right and the installation runs safely within its rated capacity from day one.

2. What Maximum Demand Means in Practice

Maximum demand is the highest electrical load your installation will draw at any point during normal operation. It drives every upstream sizing decision - from the main switchboard bus bars down to the consumer mains cable.

AS/NZS 3000:2018 Clause 2.2.2 requires you to determine the maximum demand before you size any part of the installation. The standard gives you four ways to do this:

  1. Calculation - Apply the diversity factors from Appendix C tables to each load group. This is the most common method for new commercial fit-outs.
  2. Assessment - Use engineering judgment when load patterns are complex, intermittent, or do not fit standard diversity factors. You must document your reasoning.
  3. Measurement - Record the actual peak demand over a 30-minute sustained period using a maximum demand indicator. This works best for existing buildings where you have metered data.
  4. Limitation - The maximum demand equals the fixed rating of the upstream protective device. This applies where supply authority constraints cap the available capacity.

For most new commercial projects, you will use the calculation method with Table C2 from Appendix C. Assessment comes into play on complex sites - think data centres, hospitals, or buildings with large intermittent loads like commercial kitchens.

3. How to Calculate Maximum Demand for Commercial Buildings

Step 1: List Every Load

Walk through the design drawings and list every connected load. Group them into the categories that Table C2 uses:

Step 2: Apply Diversity Factors from Table C2

Table C2 in Appendix C covers non-domestic installations - offices, shops, factories, schools, hospitals, hotels, and churches. Each load group has its own diversity factor. Here are the key principles:

Lighting loads: Apply the connected lighting load in watts, convert to amps at 230 V single-phase or 400 V three-phase, then apply the Table C2 diversity factor. A typical office lighting load sits around 10–15 W/m². For a 500 m² office floor at 12 W/m², your connected lighting load is 6,000 W or 26 A at 230 V single-phase.

Socket outlets (GPOs): Table C2 provides demand allowances per socket outlet for commercial buildings. As a guide, for 10 A GPOs the standard allows 10 A for the first point plus 5 A for each group of 20 additional points (or part thereof). For 15 A outlets, allow 10 A for one or more on a circuit. Always confirm the exact values from Table C2 for your building classification - the figures vary by occupancy type.

Motors: Take the largest motor at 100% of its full-load current. All remaining motors go in at 50%. If you have a 15 kW motor (28 A at 400 V three-phase) and three 5.5 kW motors (10.5 A each), your motor demand is 28 A + (3 × 10.5 A × 0.50) = 43.75 A.

HVAC: Air conditioning units above 10 A use 75% of connected load as the demand allowance. A 30 kW packaged unit drawing 54 A at 400 V three-phase contributes 54 A × 0.75 = 40.5 A to maximum demand.

Water heating: Storage water heaters go in at 100% of nameplate rating. A 3.6 kW storage unit adds 15.7 A at 230 V.

Cooking equipment: Do not use nameplate ratings directly. Refer to Table C5 for the correct demand factors. Commercial cooking loads use a sliding scale - the more appliances connected, the lower the percentage applied to each additional unit.

Step 3: Add the Load Groups Together

Sum all the after-diversity demand figures from each load group. This total is your maximum demand in amps.

Step 4: Convert to kVA for Supply Authority Applications

Your distribution network service provider (DNSP) will want the figure in kVA:

Single-phase: kVA = 230 × A / 1,000
Three-phase: kVA = 400 × A × 1.732 / 1,000

Worked Example - 800 m² Office Fit-Out (Three-Phase 400 V Supply)

Load Group Connected Load Diversity Factor After-Diversity Demand
Lighting (120 points, 9,600 W) 13.9 A per phase Per Table C2 10 A per phase
GPOs - 60 × 10 A outlets 60 outlets 10 A + 5 A × 2 20 A per phase
HVAC - 45 kW packaged unit (0.8 PF) 81 A 75% 60.8 A
Motors - 1 × 7.5 kW, 2 × 2.2 kW 14.3 A + 8.4 A 100% + 50% 18.5 A
Water heating - 1 × 3.6 kW 5.2 A 100% 5.2 A
Server room - 10 kVA UPS 14.4 A 100% 14.4 A
Total per phase ~129 A per phase

Maximum demand = 129 A × 400 V × 1.732 / 1,000 = 89 kVA

You would apply to your DNSP for a 100 kVA supply to allow headroom for future load growth.

4. Common Mistakes to Avoid

Adding up nameplate ratings without diversity

If you sum every nameplate in the building, you will massively oversize the supply. A 200 kVA connected load in an office might have a true maximum demand of 90–120 kVA after diversity.

Using Table C1 for commercial buildings

Table C1 covers domestic installations only. Commercial and industrial buildings must use Table C2. The diversity factors differ significantly.

Ignoring Table C5 for cooking loads

Commercial kitchens with multiple appliances need the sliding demand scale from Table C5. Using nameplate ratings for six deep fryers and four ovens will inflate your demand figure well beyond what the kitchen will actually draw.

Forgetting motor starting currents

While maximum demand is a sustained load calculation (30-minute window), you still need to check that your supply can handle motor starting inrush. A direct-on-line motor can draw 6–8 times its full-load current for a few seconds. This affects protective device selection, not maximum demand, but it catches people out.

Not checking DNSP Service and Installation Rules

Each DNSP publishes its own rules for connection applications. Some cap single-phase supplies at 63 A or 80 A. Others require three-phase above 15 kVA. Check these before you finalise your design - a recalculation after connection approval delays the project.

5. When to Use Assessment Instead of Calculation

The calculation method works for straightforward commercial fit-outs. But some buildings need the assessment method (AS/NZS 3000:2018 Clause 2.2.2):

Documentation requirement

When you use assessment, document everything. Record the assumptions, the load profiles, the operating schedules, and the basis for each diversity factor you apply. This documentation forms part of the design record and must be available for inspection.

6. Key Takeaways

Frequently Asked Questions

Which table in AS/NZS 3000 do I use for commercial building maximum demand?

Use Table C2 from Appendix C for all non-domestic installations including offices, shops, factories, schools, hospitals, hotels, and churches. Table C1 covers domestic installations only and must not be used for commercial buildings.

What are the four methods for determining maximum demand under AS/NZS 3000?

AS/NZS 3000:2018 Clause 2.2.2 provides four methods: Calculation (apply diversity factors from Appendix C), Assessment (engineering judgment for complex loads), Measurement (30-minute sustained peak from metered data), and Limitation (fixed rating of upstream protective device).

What diversity factor does AS/NZS 3000 apply to motors for maximum demand?

For general motors, the largest motor goes in at 100% of full-load current and all remaining motors at 50%. Lift motors use a different scale: largest at 125%, next at 75%, and remainder at 50%.

How do I convert maximum demand in amps to kVA for a DNSP application?

For single-phase: kVA = 230 × Amps / 1,000. For three-phase: kVA = 400 × Amps × 1.732 / 1,000. Most DNSPs require the maximum demand figure in kVA for supply applications.

When should I use the assessment method instead of the calculation method?

Use the assessment method for data centres, hospitals, buildings with large intermittent loads like cold storage or commercial laundries, and any installation where standard diversity factors from Table C2 do not reflect actual usage patterns. You must document all assumptions and reasoning.

This memo provides general guidance on maximum demand calculations under AS/NZS 3000:2018. It does not replace the standard itself. Always refer to the current edition of AS/NZS 3000 and your local DNSP requirements for project-specific compliance. CCC Engineering accepts no liability for designs based solely on this guidance without independent verification against the applicable standards.

Need this engineered for your project?

Get a scoped fee proposal within 48 hours. Chartered engineers. Registered in NSW, VIC, and QLD.

Get a Quote → 📞 0468 033 206

Related design memos