Project Snapshot

Cre8 Co engaged CCC Engineering to deliver the mechanical design for Mind Games, a high- concept retail and experiential fitout occupying two levels of a heritage-style commercial tenancy along Broadway. The project aimed to transform an existing open-plan shell into a museum-like interactive retail environment featuring themed zones, display galleries, and customer engagement spaces. CCC Engineering was tasked with developing compliant, efficient mechanical systems to support comfort, air quality, and the creative architectural vision while navigating the constraints of an existing naturally ventilated building.

Our Role

  • Mechanical Services Detailed Design for Levels 01 & 02
  • Review of architectural and structural documentation
  • System selection, sizing, and heat load analysis
  • Design of outside air and exhaust ventilation systems
  • Equipment schedules, scope of works, and tender documentation
  • NCC and AS1668.1/2 compliance certification
  • Budget estimates and contractor engagement support

Challenges & Solutions

Challenge

Existing building with limited ceiling and plant space

Solution

Compact, low-profile ductwork and plant layouts designed to maximise ceiling heights without compromising performance

Challenge

Integration with architectural design and feature lighting

Solution

Early coordination with architects to conceal services and maintain visual focus on the retail experience

Challenge

Uncertain natural ventilation performance

Solution

Mechanical systems designed to complement existing openings and ensure compliance with NCC F6D6 and J6 requirements

Results

  • Delivered a compliant and efficient design within a tight three-week design program
  • Achieved full NCC 2022 and AS1668.1/2 certification
  • Supported a smooth tender and construction phase through coordinated documentation
  • Ensured consistent thermal comfort across multiple interactive retail zones
  • Provided cost-effective solutions aligned with project budget and aesthetic goals