Fire Damper and Smoke Damper Requirements
What You Need to Know
Fire dampers and smoke dampers stop fire and smoke from spreading through ductwork. Every duct that passes through a fire-rated wall or floor needs protection. AS 1682 (the Australian Standard for fire and smoke dampers) and AS 1668.1 (fire and smoke control in buildings) set the rules. Miss a damper or install it wrong, and the fire compartment fails.
The Rules
- Every duct penetration through a fire-rated wall or floor must be protected with a fire damper or tested system (NCC 2025, C4D15 and Specification S5C11)
- All fire and smoke dampers must comply with AS 1682.1:2015 for design and testing, and AS 1682.2:2015 for installation and commissioning (AS 1668.1:2015, Cl 3.2)
- Wall-mounted fire dampers must match the insulation rating of the wall, unless connected to 2 metres of rigid duct on each side (AS 1668.1:2015, Cl 3.2.3)
- Smoke dampers must be installed within 600 mm of the smoke wall (AS 1668.1:2015)
- Fire dampers must be tested to AS 1530.4:2014 for integrity and insulation performance (AS 1682.1:2015)
- All fire and smoke dampers must be inspected under AS 1851, with 20% of dampers checked each year on a rolling 5-year cycle (AS 1851, Cl 13.4.1.4)
What This Means in Practice
Picture a mechanical riser in a 10-storey office building. Ductwork runs vertically through the shaft, with branch ducts breaking out at each level through fire-rated floors. Every one of those floor penetrations needs a fire damper. If a smoke control system also serves those floors, you need smoke dampers too, or combination fire/smoke dampers that do both jobs in one unit.
The 2-metre rigid duct rule catches many projects. A fire damper on its own does not always meet the wall's insulation rating. You either run 2 metres of rigid steel duct from the damper on each side, or you use an intumescent fire damper that swells shut in heat and meets the insulation requirement without the extra ductwork. On tight sites with limited ceiling void, the intumescent option saves space.
Access is the other big issue. AS 1851 requires ongoing inspection, and inspectors need to reach every damper. If a damper is buried above a plasterboard ceiling with no access panel, it cannot be maintained. That puts the building out of compliance. Plan access panels into the ceiling layout from the start.
Key Design Decisions
Damper Type: Mechanical, Intumescent, or Combination?
Use mechanical (curtain-type) fire dampers for standard duct penetrations where 2 metres of rigid duct is available. Pick intumescent dampers where space is tight or rigid duct lengths cannot be achieved. Use combination fire/smoke dampers at penetrations that need both fire resistance and smoke control.
The 2-Metre Rigid Duct Rule
Where a fire damper does not match the wall's insulation rating, connect it to 2 metres of rigid steel duct on each side of the penetration. If this is not possible, specify an intumescent fire damper or fire-rated duct wrap (e.g. FyreWrap) to meet the insulation requirement.
Access Panel Locations
Coordinate access panels for every fire and smoke damper during the design phase. Access panels must be large enough for inspection and must not compromise the fire rating of the ceiling or wall.
Smoke Damper Control Strategy
Connect smoke dampers to the fire detection system (AS 1670.1) and, where required, to the fire command panel. Smoke dampers are always motorised and must respond to real-time signals.
Who Needs to Know What
Need this engineered for your project?
Get a scoped fee proposal within 48 hours. Chartered engineers. Registered in NSW, VIC, and QLD.
References
- AS 1682.1:2015, Fire, smoke and air dampers — Part 1: Design, testing and marking
- AS 1682.2:2015, Fire, smoke and air dampers — Part 2: Selection, installation and commissioning
- AS/NZS 1668.1:2015, The use of ventilation and airconditioning in buildings — Part 1: Fire and smoke control in buildings
- National Construction Code 2022, Volume One, Part C4 — Protection of openings (C4D15, Specification S5C11)
- AS 1530.4:2014, Methods for fire tests on building materials, components and structures — Part 4: Fire-resistance tests for elements of construction
- AS 1851-2012, Routine service of fire protection systems and equipment (Section 13 - Fire and smoke dampers)
- AIRAH DA06, Guide to Fire, Smoke and Air Dampers